The school’s pitched roofs had deteriorated to D1 condition, with leaks disrupting teaching, creating health and safety hazards, and increasing costly reactive maintenance. A previous CIF application had narrowly missed approval, with concerns raised about value for money and risk planning. In addition, the works needed to be carefully sequenced around term time, comply with conservation area requirements, and mitigate risks such as asbestos, COVID-19 labour pressures, and Brexit-related supply chain issues.
Carré Consultancy led the full feasibility, specification, and procurement process:-
The project delivered a complete renewal of pitched roof coverings with upgraded insulation, guaranteed for 15 years and with an expected life of over 50 years. Key outcomes included:-
This “turn-key, quick win” CIF scheme demonstrates Carré Consultancy’s expertise in securing funding, managing complex statutory requirements, and delivering urgent compliance works that safeguard the learning environment.